One Tower Bridge is a luxury residential development in the heart of London right on the River Thames offering unrivalled views and the highest specifications and quality. All alongside a number of entertainment and dining options, it’s billed as one of the most sought after locations to live in London.

Hensall were brought in to complete a range of our services on the buildings marketing suite, as well as a number of residential flats and general infrastructure work.

PROJECT STATS


SERVICES UNDERTAKEN

PROJECT MANAGEMENT
BIM Design including working drawings and coordination, Site Setup.

MECHANICAL
Boosted cold water supplies, Mains cold water and Hot water distribution, LTHW heating distribution and chilled water distribution emanating from the basement. VRF Air Conditioning, Split Air conditioning, Air source heat pump and hydro units to LTHW, LTHW heating, Packaged Chiller and chilled water distribution, Fan Coil Units, Underfloor heating, Trench heating, Air Handling Unit with heat recovery, Supply and Extract Ventilation, Above Ground drainage and condensate, Sanitary ware Installation, test commissioning and documentation, BEMS and energy monitoring.

ELECTRICAL
Main and Sub Distribution System, Containment, Lighting and Emergency Lighting, Lighting Control System, Small Power, External Lighting System and Controls, Data Wiring, Fire Alarm, CCTV, Security, Disabled Alarm, AV Systems, Access Control, Disabled Refuge, Testing and Commissioning of all Systems.

CLIENT

CUSTOMER: ONE TOWER HILL

SECTOR: RESIDENTIAL

LOCATION: LONDON

PROJECT LENGTH

6 Months

PROJECT VALUE

£800,000

COMPLETION DATE

March 2014

PROJECT OVERVIEW

For this particular project, Hensall was entrusted with the project management to oversee a wide range of our electrical and mechanical services.

The mechanical side of the project saw us provide wet underfloor heating throughout, alongside a wet chilled water fan coil system to provide mechanical cooling. Ventilation was provided by local MVHR air handling units, whilst the domestic water services and drainage were connected to the landlord infrastructure. Risers were installed by Hensall and a temporary plant room set up to allow commissioning and usage of the marketing apartments. This temporary plant room was primarily based around air sourced heat pumps providing heating and domestic hot water.

In terms of electrical, we installed all lighting and containment, as well as vital building functions for security and safety. For mechanical, the team were responsible for a variety of hot and cold water functions, air conditioning, heating and drainage, amongst other aspects of the fit out.

There were a number of challenges which needed to be overcome in order to complete the project, one of which was the on-site logistics. There were also several issues with traffic due to the central London location and the need to transport equipment and machinery. All of these were dealt with by the team effectively in order to deliver the project within budget and timescales.

The nature of this project required that everything was completed to the highest specifications and using the highest quality of materials. This was, of course, not an issue for Hensall as we always seek to provide this level of service as part of any project. It did, however, mean that we needed to be extremely careful and thorough during the design phase of the project.

TESTIMONIAL

“Hensall worked closely with all parties to provide a coordinated solution including value engineering of some elements, in a complex and congested fit out environment.”